PETRON CORPORATION, Philippines

Project Name

SUPPLY AND INSTALLATION OF 3-WAY FISHER ACTUATOR VALVE AND PRESSURE REGULATOR AT PETRON PANDACAN TERMINAL

Scope of works:

  • Supply and purchase of Fisher Actuator Valve and pressure regulator
  • Fabrication and installation of tee straight spool
  • Pull-out/Re-installation of actuator valve
  • Inspection and cleaning of existing valve body
  • Assemble of actuator valve
  • Bench setting and hydrotesting of fisher valve
  • Replacement and installation of pressure regulator
  • Replacement and setting of Fisher Fieldvue Instrument  DVC 2000 (Positioner)

Project Date

January 08 – 12, 2022

Category

Supply and Replacement

PETRON CORPORATION, Philippines

Project Name

Lighting Fixtures and Panels Replacement at Calamba Warehouse

Scope of works:

  • Erection/removal of Scaffoldings
  • Warehouse Perimeter: Removal and replacement of new two (2) units 100W LED Floodlights (Weatherproof)
  • Office Perimeter: Removal and replacement of new two (2) units Weatherproof LED Lighting Fixtures
  • Inspection Area: Removal and replacement of new Four (4) units Weatherproof LED Lighting Fixtures
  • Warehouse Ceiling: Removal and replacement of new twenty five (25) units LED Lighting Fixtures
  • Mezzanine Ceiling: Removal and replacement of new twenty four (2) sets of Philips fluorescent light with starter
  • Removal and replacement of new six (6) units 2‐gang switches at the warehouse
  • Removal of old fuse box, Installation and rewiring of new 125Amps Schneider Main Circuit Breaker
  • Removal and Installation of new Weatherproof LED Lighting fixture at office entrance
  • Removal and Installation of new fluorescent light at office pantry
  • Repair and rewiring of old lighting fixture and installed at guard post area

Project Date

May 24 – 27, 2021

Category

Replacement and Installation

FCF MINERALS CORPORATION, Philippines

Project Name

Diesel Genset No. 1 Cummins KTAA 38-G9 Servicing and Installation of Radiator

Scope of works:

  • Replacement of front and rear crankshaft oil seals
  • Replacement of fuel filters, oil filters and water coolant filters
  • Engine Change Oil
  • Cleaning of Daily fuel Tank
  • Rectification of engine leaks
  • Replacement of fan belt and alternator belt
  • Adjustment of intake and exhaust valve
  • Installation of thermostat at left bank and right bank
  • Replacement of New Radiator

Project Date

March 02 – 10, 2021

Category

Servicing and Installation

PETRON CORPORATION, Philippines

Project Name

Inspection and Reconditioning of VI Bottom Mixer Agitator Motor

Scope of works:

  • Pre‐inspection of Equipment conditions
  • Pull‐out/Re-installation of Drive Motor
  • Motor Solo Run and Inspection
  • Dis‐assemble/Assemble of Motor Parts
  • Replacement of DE/NDE Bearings of motor
  • Lubrication of motor bearings
  • Inspection and Varnishing of motor windings (Additional)
  • Electrical Inspection (Resistance check, voltage, wiring connection and others)

Project Date

January 15 – 16, 2020

Category

Servicing and Installation

NIHON YAKIN, Japan

Project Name

Replacement and installation of brush roll

Project Date

December 01, 2016

Category

Installation